| Work Package # | Role | Artifact Name | Sections / Modules | C r e a t e |
A d d |
D e l e t e |
E d i t |
C o r r e c t |
A s s e m b l e |
Date Started | Date Finished | % Work Completed | Time Period Hours | Total Hours | Deliverable(s) | |
| 5.3 | Design Analyst | System Architecture | Top level description of the system. | X | 11/25/2001 | 11/25/2001 | 100% | 2 | 2 | SystemArchitecture.zip | ||||||
| 5.3 | Design Analyst | Level Two Flow Diagram (DFD) | Data flow in more detailed form | X | 11/20/2001 | 11/20/2001 | 100% | 3 | 3 | Level2DFD.zip | ||||||
| Totals | 1 | 1 | 2 | 2 | 2 | 2 | 100% | 5 | 5 | 2 | ||||||
| Work Package ID | Date / Start Time | Time Arrived | Time Left | Meeting Purpose | |
| 9.4.3.5 | 11/16/2001 2:15 PM |
2:15 PM | 3:30PM | Discuss data flow diagram, error handling, data storage format; Assigned new work to each design analyst. | |
| 9.4.3.6 | 11/19/2001 2:15PM |
2:15PM | 3:30PM | Discussed design document; Divided the detailed design into pieces and assigned them to design analysts. | |
| Totals | 2 | ||||
| Work Package # | Role | Bulleted List of Specific Tasks | Date Started | Date Finished | % Work Completed | Time Period Hours | Total Hours | |
| NA | ||||||||
| NA | ||||||||
| NA | ||||||||
| Totals | ||||||||
NA
NA
<The table entries should be filled in as follows if you are a manager or team leader:
>
| Team Member Name | Bulleted List of Progress | Bulleted List of Goals |