Weekly Review Form

ECOACH - Reading Assessment

Melyssa Boswell

Time Period:  11/05/2001 - 11/11/2001


The information given on this form represents my work on the project and is true to the best of my knowledge.


Artifact Work

Work Package # Role Artifact Name Sections / Modules C
r
e
a
t
e
A
d
d
D
e
l
e
t
e
E
d
i
t
C
o
r
r
e
c
t
A
s
s
e
m
b
l
e
Date Started Date Finished % Work Completed Time Period Hours Total Hours Deliverable(s)
5.2.5.4 design analyst design document
  • 5.2.5.4 Report Formats - could only do a small amount because i didn't exactly know what to do until today. (spent hours looking through book, internet, asking people)
x           11/10/2001 N/A 25% 5 5
  • ReportFormatsV1.htm
Totals 1 1 1 1             1 0   5 5 1

Meetings

Work Package ID Date / Start Time Time Arrived Time Left Meeting Purpose
9.4.2.5 11/09/2001 -
2:15 PM
2:05 PM 2:40 PM Team Meeting - met with some programmers also.  divided up work packages. was assigned report formats on saturday.   had to leave early to pick up daughter from school.
Totals 1        

Other Work

 

Work Package ID Role Bulleted List of Specific Tasks Date Started Date Finished % Work Completed Time Period Hours Total Hours
N/A N/A
  • N/A
N/A N/A N/A N/A N/A
Totals 0 0 0 0 0   0 0

Problems and Comments


Managers and Leaders

Team Member Name Bulleted List of Progress Bulleted List of Goals
N/A - team member
  • N/A
  • N/A