| Work Package # | Role | Artifact Name | Sections / Modules | C r e a t e |
A d d |
D e l e t e |
E d i t |
C o r r e c t |
A s s e m b l e |
Date Started | Date Finished | % Work Completed | Time Period Hours | Total Hours | Deliverable(s) | |
| 4.1.5.1 | Requirements Analyst | Requirements Document |
|
X | 11/02/2001 | 11/05/2001 | 90% | 3 | 3 |
|
||||||
| Totals | 1 | 1 | 1 | 2 | 1 | 1 | 3 | 3 | 2 | |||||||
| Work Package ID | Date / Start Time | Time Arrived | Time Left | Meeting Purpose | |
| 9.1.1.2 | 10/30/2001 / 09:30 AM |
09:30 AM | 10:00 AM | General team meeting to define member roles. | |
| 9.3.1.2 | 10/30/2001 / 08:00 PM |
08:00 PM | 09:00 PM | Requirements Team meeting to discuss preliminary client needs, raise questions to be asked at client meeting, and choose members to attend client meeting. | |
| 9.7.1.5 | 11/02/2001 / 10:00 AM |
10:00 AM | 11:00 AM | Meeting with client to discuss client needs more specifically and ask questions raised in Requirements Team meeting. | |
| 9.3.1.5 | 11/02/2001 / 8:00 PM |
08:00 PM | 09:30 PM | Requirements Team meeting to define individual assignments to members. Also discussed detail of client meeting and began defining some requirements. | |
| Totals | 4 | ||||
| Work Package ID | Role | Bulleted List of Specific Tasks | Date Started | Date Finished | % Work Completed | Time Period Hours | Total Hours | |
| 10.4.1.2 | Requirements Analyst |
|
10/30/2001 | 11/2/2001 | 100% | 2 | 2 | |
| Totals | 1 | 1 | 2 | 1 | 1 | 2 | 2 | |