Weekly Review Form

E-COACH - Reading Assessment

Stephen Hill

Time Period:  3/26/2002 - 4/1/2002


The information given on this form represents my work on the project and is true to the best of my knowledge.


Artifact Work

Work Package # Role Artifact Name Sections / Modules C
r
e
a
t
e
A
d
d
D
e
l
e
t
e
E
d
i
t
C
o
r
r
e
c
t
A
s
s
e
m
b
l
e
Date Started Date Finished % Work Completed Time Period Hours Total Hours Deliverable(s)
4.2.1.4 Programmer Program Evaluation of this tool X           3/25/2002 4/01/2002 100% 2 2 2365Hill,StephenLWR04022002.zip

eval.asp

 

Totals 1 1 1 1             1 1   2 2 1

Meetings

Work Package ID Date / Start Time Time Arrived Time Left Meeting Purpose
9.1.2.5 04/02/2002 8:30 AM 9:20 AM General team meeting

Purpose: Briefly discuss project completion.  Discuss new changes with the requirements team.

Totals 1        

Other Work

Work Package ID Role Bulleted List of Specific Tasks Date Started Date Finished % Work Completed Time Period Hours Total Hours
4.0.3.1 Programming
  • Continue to Learn ASP
  • Continue reviewing JScript
  • Briefly review Forms
03/04/2002 N/A 80% 2 8
Totals 1 1 1 1 0 6 2 10

Problems and Comments