End-Of-Semester Document
ECOACH - Reading Assessment
J. Ryan Dyer
Table of Contents
Accomplishments
- The Requirements document was finalized
- The Design document is near completion; all but some of the detailed
designs was completed.
- The Software Manual was updated for the current code that was created
- The Software Code is near completion; most graphical screens have been
done.
Problems Encountered
- Some members of teams did not fully participate in the project.
- Miscommunication between teams. Ensure as software manager that all
teams are on the same page even if you think they are. More
communication is better than lack of.
Software Process Improvements
<List of recommendations on how to improve the project process broken down
by role. Use bulleted lists.>
Recommendations for Next Semester
- First, start off by having the team review and understand the requirements
document.
- Then move on to the design document. Finish the detailed designs for
it.
- With people that aren't working on detailed designs, assign some of them
to start working on testing while a few finish the needed software code.
To Do List
Team Request Forms
Revision History
| Date |
Name |
Revision |
| 11/28/2001 |
J. Ryan Dyer |
Initial Draft |
| |
|
|
| |
|
|