ME 317 Design for Manufacturing
Schedule: Winter 2010-1
|
Day |
|
Reading |
Lecture |
Assignments |
Resources |
|
1 (11/28) |
General Principles of DFM |
1.3, Syllabus |
|
||
|
2 (11/29) |
Economics of Process Selection Characterization of Part Geometry (metrology, tolerances, surface finish) |
1.2 |
|||
|
3 (12/1) |
Metal Extrusions Roll Forming |
3.1 3.11 |
|||
|
4 (12/5) |
Metal Stampings |
3.2 |
|
||
|
5 (12/6) |
Bending |
|
|
|
|
|
6 (12/8) |
Powder Metal Parts |
3.12 |
|||
|
7 (12/12) |
Forgings |
3.13 |
|||
|
8 (12/13) |
Tolerance Stack-ups |
|
Mini-project 1 Due |
||
|
9 (12/15) |
Project Day |
|
Assigned |
|
|
|
10 (12/19) |
Geometric Dimensioning and Tolerancing |
|
|
|
|
|
11 (12/20) |
Exam 1 |
|
|
||
|
12 (1/5) |
Intro to Machining, Hole Making |
4.34.5 |
|
||
|
13 (1/9) |
Turning, Milling |
4.3, 4.44.6 |
|
|
|
|
14 (1/10) |
Milling, Grinding |
4.13,14,15 |
|
|
|
|
15 (1/12) |
Sand Casting |
5.1 |
|
||
|
16 (1/16) |
Investment Casting |
5.3 |
|
Mini-Project 2 Due |
|
|
17 (1/17) |
Die Casting |
5.4 |
|
||
|
18 (1/19) |
Rapid Prototyping |
|
|
||
|
19 (1/23) |
Plastic Injection Molding |
6.2 |
Mini-Project
4 Assignment |
||
|
20 (1/24) |
Rotational Molding Blow Molding Thermoforming |
6.4 6.5 6.8 |
|
||
|
21 (1/25) |
Exam 2 |
|
|
|
|
|
22 (1/26) |
Snap-fits Living Hinges Assembly techniques for polymers |
|
|||
|
23 (1/31) |
Joining |
|
|
||
|
24 (2/2) |
Design for Assembly |
|
Mini-Project 3 Due |
||
|
25 (2/6) |
Poka Yoke (mistake proofing) |
|
|
||
|
26 (2/7) |
Product structure |
|
|
|
|
|
27 (2/9) |
Six Sigma, Cp, Cpk |
|
|
||
|
28 (2/13) |
Statistical process control |
|
|
||
|
29 (2/14) |
Robust Design |
|
|
Mini-Project 4 Due |
|
|
30 (2/16) |
Contingency/Evals |
|
|
|
|