Individual Weekly Report Form
Brett Dymond
Time Period: 1/27/03 - 2/02/03
The information given on this form
represents my work on the project and is true to the best of my knowledge.
Tasks completed:
- Met with Group on Monday
- Met with Gary Adler
- Finally squared computer away, 4 partitions, 2 operating systems, 2 simulated network drives
- Tried to work with macros using given passwords with no success
- Experimented with various dialogs and menu interfaces using lotus script
Total time spent this week: 5 hours 15 minutes
Unfinished tasks:
- Meet with programming group and establish plan of attack
- Subdivide workload
- Meet with Testing Team
- Create project outline in MSProject
Estimated amount of time to complete unfinished tasks: 2 hour 30 minutes
Problems, concerns, possible major risks,
and general comments:
- We finally have all of the software and computer systems needed.
- In this next week I believe we can make a lot of progress namely towards:
- repairing the macros
- setting up the testing macros using lotus script
- establishing sub-project plans using Microsoft Project
- We have reached a point where all groups can start working at 100% capacity