Team 8 Weekly Report Summary
Joshua Hertz
Time Period: 01/20/03 – 01/26/03
The information given on this form
represents my work on the project and is true to the best of my knowledge.
Tasks Completed By Team During the Last Time
Period:
- Weekly Monday meeting
- Meeting with Client about
Computer/Software
- Meeting of Programming Team
- Studied Lotus Scripting
Language
-
Total time spent by
team: 355 mins
Unfinished Tasks:
- Preliminary test plan
- Determine viablility
of Visual Basic script tests
- Still need to get computer
set up properly
Estimated time to complete unfinished tasks: 540
Tasks To Be Performed Over the Next Week:
- Get Software/Working Computer
- Waiting on code and/or Requirements
Specification Document to begin work on Unfinished tasks.
Problems, concerns, possible major risks,
and general comments:
- When are we going to get the
software from the client
Notes:
- This report was compiled
without reports from Brett and Mike as
they were never turned in.