Time Period: 12/16/02 – 12/20/02
The information given on this form
represents my work on the project and is true to the best of my knowledge.
Tasks Completed By Team During the Last Time
Period:
- Monday Meeting with Mark
- Studied Lotus Scripting
Language
- Developed some
testing/verification algorithims
Total time spent by
team: 305 mins
Unfinished Tasks:
Estimated time to complete unfinished tasks: 0
Tasks To Be Performed Over the Next Week:
- Get Software and break into
smaller teams
Problems, concerns, possible major risks,
and general comments:
- When are we going to get the
software from the client?