Team 8 Weekly Report Summary
Joshua Hertz
Time Period: 05/05/03 – 05/11/03
The information given on this form
represents my work on the project and is true to the best of my knowledge.
Tasks Completed By Team During the Last Time
Period:
- Wrote Presentation
- Began Testing
- Finished Programming
Total time spent by
team: 940 minutes (note: most people did not turn in weekly reports this
week)
Unfinished Tasks:
Estimated time to complete unfinished tasks: ~1 weeks
Tasks To Be Performed Over the Next Week:
- Test all the Macros
- Deliver the Final Product
Problems, concerns, possible major risks,
and general comments:
Notes:
- Most people did not turn in
weekly reports this week.