Individual Weekly Report Form
Stuart Ford
Time Period: 3/31/03 - 4/06/03
The information given on this form represents my work on the project and is true to the best of my knowledge.
Tasks completed:
- Wed Team Meeting
- Reviewed Macros for master programming todo list
- Installed Lotus1-2-3 on my laptop
Total time spent this week: 120 min
Unfinished tasks:
Estimated amount of time to complete unfinished tasks: 40 min
Problems, concerns, possible major risks, and general comments:
- As of this writing (late Sunday night) I haven't received any lists from the programming team...
- You can use the machine in the imaging lab to look at the macros... you don't have to have it installed on your local machine.
- Is the website reflecting current members yet? (about us page?)