Team 8 Weekly Report Summary
Joshua Hertz
Time Period: 12/09/02 – 12/14/02
The information given on this form
represents my work on the project and is true to the best of my knowledge.
Tasks Completed By Team During the Last Time
Period:
- Initial Meeting
- Client Meeting
- Planning Meeting
Total time spent by
team: 28.5
Unfinished Tasks:
Estimated time to complete unfinished tasks: 0
Tasks To Be Performed Over the Next Week:
Problems, concerns, possible major risks,
and general comments: